Search BPC
Search for content, licensing, rules, regulations, building issues or anything else.
A respondent who receives a payment claim must pay the amount claimed in full by the due date for payment or give the claimant a payment schedule within 10 business days after being served with the claim (or sooner, if the contract sets a shorter deadline).
If you are the claimant, you can take action against a respondent if the respondent:
You have several options, including:
A lien is a form of security over property where one party retains ownership of the property as security for the performance of an obligation by the other party. A lien can only apply to property that is physically transferable, for example, unfixed goods and materials.
If a progress payment becomes due and payable, you are entitled to exercise a lien in respect of the unpaid amount over any unfixed plant or materials that you have supplied to the respondent for use in connection with carrying out construction work for the respondent.
As the claimant, you retain ownership of the unfixed plant or materials until the respondent pays any outstanding progress payment that is due.
You need to serve a Notice of intention to exercise lien on the respondent in a particular form. The form is prescribed in the Building and Construction Industry Security of Payment Regulations 2023 (the SOP Regulations).
The Notice of intention to exercise lien can be served in any of the following ways:
Please note that the information on this page is provided for general guidance only and must not be regarded as legal advice. Before exercising a lien, the claimant is advised to seek legal advice.
Contact the Law Institute of Victoria for referral to a solicitor.
Upon receiving the Notice of intention to exercise lien, the respondent is not entitled to fix, remove, sell or otherwise deal with the unfixed plant or materials identified in the Notice until you have received the outstanding progress payment.
As the claimant, you become a secured creditor. This means that the unfixed plant or materials will not be available for payment of unsecured creditors in any distribution of assets by an external administrator.
The lien does not give you any right against any third party who is, or has become, the owner of the unfixed plant or materials.
The lien in respect of the unpaid amount ceases when you receive the progress payment.
The claimant has a right to suspend work or the supply of goods and services to the respondent until the amount payable has been paid. You must give the respondent three business days’ written notice of the suspension. The notice must state that it is made under the SOP Act. A claimant who exercises this right in accordance with the SOP Act is not liable for any consequential loss or expense suffered by the respondent.
Adjudication is a process created by the SOP Act to resolve a disputed claim for payment due under a construction contract. For more information see SOP Adjudication.
Instead of applying for adjudication, you may choose to go to court to recover an unpaid amount.
For example, if the respondent does not pay you in accordance with their payment schedule, or has given you a payment schedule showing they propose to pay less than the amount you claimed, you may decide to go to court rather than apply for adjudication.
You can commence proceedings in court for any dispute that may otherwise be adjudicated under the SOP Act.
This is done by lodging a complaint in the Magistrates’ Court or a writ in the County Court or Supreme Court (depending on the amount owed) and paying a filing fee, if any. Your lawyer can advise you about this process.