Search BPC
Search for content, licensing, rules, regulations, building issues or anything else.
If you have been served with an adjudication application, an adjudication response is your reply to the application.
You may lodge an adjudication response only if you served a payment schedule or performance security schedule in accordance with the SOP Act.
An adjudication response must:
A person is a relevant principal of the respondent if:
Note: This does not include the principal in a domestic building contract. Domestic building contracts between a builder or supplier and the home owner are not covered by the SOP Act. These come under the Domestic Building Contracts Act 1995.
The adjudicator must notify any relevant principal of the adjudication application.
The adjudicator must also notify any other person identified in the adjudication response and any person the adjudicator reasonably believes, on the basis of any submission from the claimant or the respondent, is a person who has a financial or contractual interest in the adjudication application of the application.
The adjudication response may contain any submissions relevant to the response that you choose to include. Copies of documents relevant to the submissions should be attached.
You cannot include in your adjudication response any reasons for withholding payment or release that were not provided in the payment schedule or performance security schedule. The adjudicator will not be able to consider any reasons that were not included in a schedule.
You must lodge the adjudication response with the adjudicator within 5 business days after receiving a copy of the adjudication application from the claimant, or 2 business days after receiving notice of an adjudicator’s acceptance of the application – whichever is later.
You must also serve a copy of the response, including any attachments, on the claimant no later than 3 business days after the response is lodged with the adjudicator.
The claimant’s copy of the adjudication response can be served in the manner (if any) required by the construction contract. In any other case, it can be served by one of the following means:
The adjudication response can also be served on the claimant’s agent.